Process order header material: HR0072

BOM item materials:

  1. RR0078
  2. R0078A
  3. R0880A

 

Control cycle master data: they are all pick parts.

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

  1. create& release process order, M36040

 

 

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Release process order, TR was created: 271122.

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Convert TR to TO, TO 245032.

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

LT12 to confirm this TO,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Save it. The batch of components are updated into process order,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

  1. MB1A to issue components to process order, this is planned goods issue,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Save it,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

  1. We can find the stock in PSA storage type was consumed:

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

  1. If business team need consume more raw material than planned quantity, maybe need to consume another batch, for example, need to consume more quantity 1 KG for the raw material RR0078, another batch 2002000057.

4.1) Then LB01 to create TR by manually, with WM movement type 997(or SAP standard movement type 319),

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

TR 271123,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

4.2)  Convert this TR to TO document,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

At this moment, the new batch 2002000057 will NOT be updated into process order since it was unplanned.

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

4.3) Then MB1A + 261 , try to do planned goods issue.

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Failed. We cannot do planned goods issue for this process order now.

 

Try to do unplanned goods issue,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Enter,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Save it, see the WM details data for this material document item,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

The raw material was consumed from GI storage type, but not from PSA storage type.

That’s the difference of WM level effect between planned GI and unplanned GI to process order.

 

4.4) The WM stock status for this material/batch combination,

SAP PP 计划外发料与计划内发料在WM层面的差异初探

There is 1 KG in PSA storage type, but -1 KG in GI storage type.

 

We need to do bin to bin stock transfer (LT01+999) from PSA to GI area in order to adjust stock balance.

 